#

Grid reinforcement

Project setup
Peak Shaving

Main results

  • Restaurant opened earlier
  • No roaring generator on the terrace
  • No inconvenience to local residents
  • Complete installation by Greener

Overpowered grid connection

The Wurst und Schnitzelhouse opens new shops in Amsterdam, but cannot get the necessary electricity infrastructure from the grid operator quick enough. On the busy Zuidas, a diesel generatorwould cause too much inconvenience for local residents and guests on the terrace.

“Opening a new shops is always an exciting time for us. The use of the battery is new to us, but fortunately went smooth.”
Daniëlle Weeling
Manager Wurst und Schnitzelhouse

Peak shaving with a battery

Greener has deployed a battery that can peak shave on the existing installation that is not powerful enough. This installation has enough capacity throughout the day to supply all kWh, and together with the battery it is strong enough to handle the restaurant’s peak consumption.

Jon Sexstone

Business Developer

Copy email
+44 79 70 93 33 87

Request a quote
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.